STARTED: 2026-05-06 09:41:48
=== Clearing old PM seed data ===
Done.

=== Inserting 5 Projects ===
  Project #9: Mumbai Metro Rail Corridor Phase 3
  Project #10: Pune–Nashik NH-50 Highway Widening
  Project #11: Nagpur Smart City Water Supply
  Project #12: Ahmedabad Industrial Park Phase 2
  Project #13: Hyderabad IT Park & Township

=== Inserting 5 Phases ===
  Phase #1: Phase 1: Civil & Structural Works (project #9)
  Phase #2: Phase 1: Earthworks & Subgrade (project #10)
  Phase #3: Phase 1: Pipeline Laying & Testing (project #11)
  Phase #4: Phase 1: Site Preparation & Grading (project #12)
  Phase #5: Phase 1: Foundation & Basement (project #13)

=== Inserting 10 Milestones ===
  Milestone #1: Station Box Excavation Complete (phase #1)
  Milestone #2: Tunnel Boring Machine Launch (phase #1)
  Milestone #3: 50% Earthwork Completion (phase #2)
  Milestone #4: Granular Sub-base Laying Done (phase #2)
  Milestone #5: Zone A Pipeline Complete (phase #3)
  Milestone #6: Pump House Commissioning (phase #3)
  Milestone #7: Boundary Wall Completion (phase #4)
  Milestone #8: Internal Roads & Drainage Done (phase #4)
  Milestone #9: Piling Works Complete (phase #5)
  Milestone #10: Basement Raft Slab Poured (phase #5)

=== Inserting 20 Tasks ===
  Task #1: Diaphragm Wall Construction (milestone #1)
  Task #2: Excavation to Formation Level (milestone #1)
  Task #3: TBM Assembly & Testing (milestone #2)
  Task #4: Launch Shaft Preparation (milestone #2)
  Task #5: Clearing & Grubbing – Km 0–105 (milestone #3)
  Task #6: Embankment Filling – Km 0–105 (milestone #3)
  Task #7: WMM Layer Spreading & Rolling (milestone #4)
  Task #8: GSB Compaction Quality Check (milestone #4)
  Task #9: Trenching – Zone A (30 km) (milestone #5)
  Task #10: Pipe Laying & Jointing Zone A (milestone #5)
  Task #11: Pump House Civil Works (milestone #6)
  Task #12: Pump Set Procurement & Install (milestone #6)
  Task #13: Perimeter Survey & Pegging (milestone #7)
  Task #14: Boundary Wall Masonry Works (milestone #7)
  Task #15: Storm Water Drain Layout (milestone #8)
  Task #16: Subgrade Preparation Roads (milestone #8)
  Task #17: Pile Rig Mobilisation & Setup (milestone #9)
  Task #18: Bored Piling Works – Tower A (milestone #9)
  Task #19: Pile Cap Construction (milestone #10)
  Task #20: Basement Raft Formwork & Pour (milestone #10)

=== SEED COMPLETE ===
Projects: 5 → IDs: 9, 10, 11, 12, 13
Phases:   5 → IDs: 1, 2, 3, 4, 5
Milestones: 10
Tasks: 20
Gantt chart URL for project 1: http://localhost/Rajpath%20civitas/projects/9/gantt
=== Clearing old PM seed data ===
Done.

=== Inserting 5 Projects ===
  Project #9: Mumbai Metro Rail Corridor Phase 3
  Project #10: Pune–Nashik NH-50 Highway Widening
  Project #11: Nagpur Smart City Water Supply
  Project #12: Ahmedabad Industrial Park Phase 2
  Project #13: Hyderabad IT Park & Township

=== Inserting 5 Phases ===
  Phase #1: Phase 1: Civil & Structural Works (project #9)
  Phase #2: Phase 1: Earthworks & Subgrade (project #10)
  Phase #3: Phase 1: Pipeline Laying & Testing (project #11)
  Phase #4: Phase 1: Site Preparation & Grading (project #12)
  Phase #5: Phase 1: Foundation & Basement (project #13)

=== Inserting 10 Milestones ===
  Milestone #1: Station Box Excavation Complete (phase #1)
  Milestone #2: Tunnel Boring Machine Launch (phase #1)
  Milestone #3: 50% Earthwork Completion (phase #2)
  Milestone #4: Granular Sub-base Laying Done (phase #2)
  Milestone #5: Zone A Pipeline Complete (phase #3)
  Milestone #6: Pump House Commissioning (phase #3)
  Milestone #7: Boundary Wall Completion (phase #4)
  Milestone #8: Internal Roads & Drainage Done (phase #4)
  Milestone #9: Piling Works Complete (phase #5)
  Milestone #10: Basement Raft Slab Poured (phase #5)

=== Inserting 20 Tasks ===
  Task #1: Diaphragm Wall Construction (milestone #1)
  Task #2: Excavation to Formation Level (milestone #1)
  Task #3: TBM Assembly & Testing (milestone #2)
  Task #4: Launch Shaft Preparation (milestone #2)
  Task #5: Clearing & Grubbing – Km 0–105 (milestone #3)
  Task #6: Embankment Filling – Km 0–105 (milestone #3)
  Task #7: WMM Layer Spreading & Rolling (milestone #4)
  Task #8: GSB Compaction Quality Check (milestone #4)
  Task #9: Trenching – Zone A (30 km) (milestone #5)
  Task #10: Pipe Laying & Jointing Zone A (milestone #5)
  Task #11: Pump House Civil Works (milestone #6)
  Task #12: Pump Set Procurement & Install (milestone #6)
  Task #13: Perimeter Survey & Pegging (milestone #7)
  Task #14: Boundary Wall Masonry Works (milestone #7)
  Task #15: Storm Water Drain Layout (milestone #8)
  Task #16: Subgrade Preparation Roads (milestone #8)
  Task #17: Pile Rig Mobilisation & Setup (milestone #9)
  Task #18: Bored Piling Works – Tower A (milestone #9)
  Task #19: Pile Cap Construction (milestone #10)
  Task #20: Basement Raft Formwork & Pour (milestone #10)

=== SEED COMPLETE ===
Projects: 5 → IDs: 9, 10, 11, 12, 13
Phases:   5 → IDs: 1, 2, 3, 4, 5
Milestones: 10
Tasks: 20
Gantt chart URL for project 1: http://localhost/Rajpath%20civitas/projects/9/gantt
